Mixer, the operator should learn and master the structure of the
mixer mixing system, performance, operating procedures, familiar with the operation and technical specifications of safety, familiar with computer basic operation, basic understanding of the quality requirements of raw materials and the main performance, specifications, functions, and the superior company actual inspection qualified rear can install shield.
2.
The preparation for blender run 1)
Check hand-over records, and check whether the raw materials warehouse changes;
2)
Check whether mixing equipment and supporting facilities condition is good, if the water is normal.
Find fault, not to work in spite of;
3)
According to the requirements in a timely manner filling grease and lubricating oil;
4)
In accordance with the order through to the power operation station.
Check the instrument, instrument, signal, air pressure, voltage is normal;
5)
Check the measuring sensor system meets the technical requirements, and in accordance with the provisions for routine calibration.
Cooperate with quality department to into the action of static mixer metering equipment daily check, fill in relevant records;
6)
No-load test, check the mechanical equipment is working correctly.
3.
According to the mixing ratio to inform input data into the computer, before starting the production check and obtain the signature of the tester.
4.
Under the guidance of laboratory personnel adjustment slump, pay attention to in the process of normal production per the appearance quality of concrete machine, notice if any abnormal test personnel processing.
5.
Should print operation record, at the same time the production (diary
Mixer production records)
。
6.
Operation are strictly forbidden to repair and adjust the blender.
7.
Mixer at the end of the run should be cleaned up and to clean the work site to maintain the cleanliness of the mixer.
The pollution of air compressor should be, should cut off power supply before work.
8.
Mixer, belt machine, air compressor, such as maintenance, equipment and facilities for original materials storehouse clean must cut off power supply, hang warning signs.
In the process of mixing and maintenance, the maintenance personnel must use lock the operating indoor power distribution cabinet lock, can only use the monitor in operation.
9.
Mixer and auxiliary equipment, the facility operator must go through security technology training and post training, examination qualified to mount guard.
All personnel must also accept re-education on a regular basis.
What are the rules of mixer operation process
Looking for a producer to fix your chemical reactor problems? Then contact the chemical reactor experts at Guangdong
Jinzong Machinery Co., Ltd., offering a wide range of products across the global market. Visit Jinzong Machinery to find our best offer!
Guangdong
Jinzong Machinery Co., Ltd. would like to provide our customers with as near perfect protection, as near perfect service as is humanly possible and to do so at the lowest possible cost.'
To offer abundant options of product is an important factor to a company, such as chemical reactor
cosmetic machinery manufacturers to afford high-quality products for customers.
If you are looking for best product, then here are some product like chemical reactor,
cosmetic machinery manufacturers and cosmetic machinery manufacturers in various styles which will surely meet your demand. Visit Jinzong Machinery to know more!
Guangdong Jinzong Machinery Co., Ltd. has never compromised on the quality and the services provided to the customer.